Decision Maker: Leader of the Council
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: Yes
To extend the longstop date to 31 October 2022.
RESOLVED that the longstop date for the completion of the running track at Carver Barracks be extended to 31 October 2022.
The project is well underway but will not be completed by the current longstop date of 30 June 2022.
Discussions on a drainage issue have delayed the completion
None.
Publication date: 24/05/2022
Date of decision: 24/05/2022
Effective from: 01/06/2022